Public Needs to Be Informed About Project Labor Agreement for Measure L Projects at Cuesta College

Here’s my email to the Cuesta College (San Luis Obispo Community College District) elected board of trustees and top administrators regarding the sneaky effort to require its construction contractors to sign a “Project Labor Agreement” with unions as a condition of working on projects funded by Measure L. In November 2014, 62.6% of voters authorized the district to borrow $275 million for construction projects by selling bonds to investors.


Subject: Public Needs to Be Informed About Project Labor Agreement for Measure L Projects at Cuesta College
From: Kevin Dayton
Date: February 2, 2015 at 2:42:59 PM PST

Dear Cuesta College Board of Trustees:

I haven’t been able to find any official information provided to voters before Election Day about the plan of Cuesta College to require construction companies to sign a “Project Labor Agreement” with unions as a condition of working on projects funded by Measure L.

To try to alert taxpayers, students, and other interested parties about the Project Labor Agreement plan, I have provided concise information about it to various media entities, including the San Luis Obispo Tribune, KSPY, KCOY, KEYT, KVEC News/Talk 920, the Tolusa Press newspapers, CalCoastNews.com, New Times SLO, the Cuestonian, and Paso Robles Daily News. See below.

Since you had a representative of the Tri-Valley Building and Construction Trades Council make a presentation to the board after Measure L passed, I suggest you invite some local construction company representatives to make a presentation, so that you have a range of viewpoints on this highly-controversial and costly proposal. Were local construction trade associations informed about the December 10 Project Labor Agreement presentation?

Also, shouldn’t Cuesta College officially inform ordinary citizens about the Project Labor Agreement plan, since they will be paying back the principal and interest on the borrowed money obtained through bond issues? I don’t see any News Releases from Cuesta College about it.

Kevin Dayton
President and CEO
Labor Issues Solutions, LLC

———
EXAMPLE

From: Kevin Dayton
Subject: Cuesta College board mtg 2/4 – proposal for union monopoly on construction funded by Measure L
Date: February 2, 2015 at 11:55:28 AM PST
To: xxx

Cuesta College board of trustees is discussing at its February 4 meeting whether its construction contractors should be required to sign a “Project Labor Agreement” with the Tri-Valley Building and Construction Trades Council as a condition of working on projects funded by Measure L.

http://www.boarddocs.com/ca/cuesta/Board.nsf/goto?open&id=9T2V5K7C869E

This plan was kept quiet until 62% of voters approved the bond measure last November. Then the construction unions were invited to make a one-sided presentation about Project Labor Agreements:

http://www.boarddocs.com/ca/cuesta/Board.nsf/goto?open&id=9R3RYG704625

Project Labor Agreements cut bid competition and raise construction costs for the benefit of unions. Here is a 2011 study from the National University System Institute for Policy Research: “Our research shows that PLAs are associated with higher construction costs. We found that costs are 13 to 15 percent higher when school districts construct a school under a PLA.”

http://www.nusinstitute.org/assets/resources/pageResources/Measuring-the-Cost-of-Project-Labor-Agreements-on-School-Construction-in-California.pdf

Your readers might be interested in this proposed policy. Voters had no idea last November that this union plan was going to happen.

Kevin Dayton